“Progress in the Caculo Cabaça project was emphasized by the Energy Minister last Friday, 02 February 2024.”

On February 2nd, 2024, João Baptista Borges, the Minister of Energy and Water, briefed on the advancements of the Caculo Cabaça hydroelectric dam project within Cambambe, Kwanza Norte. This update followed a session with the Technical Committee tasked with the project’s oversight. Borges emphasized the progress in carving out two water return tunnels and a separate tunnel for turbine hall access. These tunnels, measuring five kilometers in length and 16 meters in width, play a crucial role in housing the turbines. The construction milestones for these tunnels have reached about 22% and 11% completion, respectively.

Borges shed light on the intricate challenges of tunnel drilling, foreseeing delays across different project areas due to essential adjustments for timeline adherence. Unforeseen technical and geological hurdles have surfaced, contributing to these delays. Financial hurdles, including delays in payments to key inspectors or designers crucial for project verification and meeting deadlines, were also pinpointed as significant challenges. Borges pledged to work in tandem with the Ministry of Finance to resolve these financial issues and advocated for continuous collaboration among project participants to avert further delays.

In spite of these hurdles, the project director, Augusto Chico, revealed that the dam’s construction has achieved approximately 14.07% physical completion and 15% financial completion. He recognized the extensive infrastructure work completed thus far, which is anticipated to hasten the construction phase. Energy production at the Caculo Cabaça dam is anticipated to commence in October 2026 with the operationalization of the first turbine.

Initiated in 2017 with a budget surpassing five billion dollars, the project currently employs around 2,500 individuals, encompassing both local and foreign workers. It receives substantial financial support from the People’s Republic of China, contributing 4.5 billion dollars towards the civil works of the hydroelectric facility and its associated transport systems, and Germany, which has provided 1.02 billion dollars for the procurement and assembly of electromechanical components.

Expected to generate 2,172 megawatts (MW) of power, the Caculo Cabaça hydroelectric initiative will join the network of dams along the mid-section of the Kwanza River, alongside others such as Cambambe (Cuanza Norte), Capanda, and Laúca (Malanje). The project’s construction is under the stewardship of the China Gezhouba Group Corporation, a state-run entity. Beyond participating in the meeting, João Baptista Borges also reviewed the progress of construction efforts at the site, including the primary power station, tunnels, the dam itself, construction yards, bridges, and additional structures.

New Poll Shines Important Light On The Deep State Rising In The Second Trump...

A surprising number of federal bureaucrats who work in Washington, D.C., plan to oppose President Donald Trump from within the The post New Poll Shines Important Light On The Deep State Rising In The Second Trump Admin appeared first on The Political Insider.

DOJ: Noncitizen IL Officials Kept From ICE Accused Of Murder After Jail Release

One of several examples the U.S. Department of Justice gave of how federal officials have been obstructed by Illinois’ migrant The post DOJ: Noncitizen IL Officials Kept From ICE Accused Of Murder After Jail Release appeared first on The Political Insider.

Waste Of The Day: NY Staircase Costs Almost $1 Million Per Step

Topline: Every journey starts with a single step, but the cost of each step isn’t usually $935,000. That’s how much New The post Waste Of The Day: NY Staircase Costs Almost $1 Million Per Step appeared first on The Political Insider.

Poll: 7 In 10 Americans To Celebrate Easter This Year

Nearly 70% of Americans plan to celebrate Easter in some form this year, according to new polling. Of the 69% The post Poll: 7 In 10 Americans To Celebrate Easter This Year appeared first on The Political Insider.

WATCH: Mother Of Maryland Woman Murdered By MS-13 Gang Member Details Gruesome Attack

In a last-minute press briefing Wednesday afternoon, the mother of Rachel Morin, a 37-year-old Marylander who was raped and murdered The post WATCH: Mother Of Maryland Woman Murdered By MS-13 Gang Member Details Gruesome Attack appeared first on The Political Insider.

White House Prepares To Go After Noncitizens Who Defraud Entitlement Programs

The White House said Tuesday it plans to help protect Social Security benefits from noncitizens and ramp up anti-fraud efforts. The post White House Prepares To Go After Noncitizens Who Defraud Entitlement Programs appeared first on The Political Insider.